Week - 1 |
Wastewater treatment plant- general principles |
Week - 2 |
Fundamental informations- the plant position choosing criteria |
Week - 3 |
Fundamental informations-the population projection |
Week - 4 |
Fundamental informations- the flow calculations |
Week - 5 |
Plant Equipments- the entrance structure planning |
Week - 6 |
Midterm week I |
Week - 7 |
Plant Equipments-the coarse/fine screening and grit removal unit planning |
Week - 8 |
Plant Equipments-equilization and primary sedimantation tank planning |
Week - 9 |
Plant Equipments-biological treatment unit and secondary settling tank planning |
Week - 10 |
Plant Equipments- disinfection unit planning |
Week - 11 |
Plant Equipments- sludge dewatering unit planning |
Week - 12 |
Midterm week II |
Week - 13 |
Plant Equipments-sludge digestion unit and outlet pipe planning |
Week - 14 |
Wastewater treatment plant- the other units and making a general evaluation. |